Contents
Snagging in Dubai is inspecting a new property for defects (snags) at handover and sending the developer a snag list to fix. The law backs it up: under Law No. 6 of 2019 the developer must repair defective installations such as electrical, plumbing and mechanical works for one year from handover, and structural defects for ten years from the project's completion certificate. The escrow law also holds back 5% of the project account for a year as a guarantee for defects.
- Installations: 1 year from handover
- Structure: 10 years from completion certificate
- Escrow retention: 5% for 1 year
- Area shortfall: Compensation beyond 5%
Snag meaning: what is snagging?
A snag is a defect or unfinished item in a new building: a cracked tile, a door that does not close, a leaking tap, a socket that does not work. Snagging is the process of finding and recording them, and the snag list (or snag report) is the document you give the developer. De-snagging is the follow-up: checking that each item was actually fixed. These are construction terms, not legal ones; the law speaks of defects in installations and structure.
Snagging and the law in Dubai
| Rule | What it covers | From when |
|---|---|---|
| Installations, 1 year | Repair or replacement of defective installations: mechanical, electrical, sanitary, sewerage and similar | Handover of the unit (or the completion certificate if the owner refuses to take it) |
| Structure, 10 years | Remedying defects in the structural parts of the building | The project's completion certificate |
| Escrow retention, 5% | 5% of each escrow account kept as a guarantee for defects | Released one year after units are registered to buyers |
Law No. 6 of 2019, Article 40; Law No. 8 of 2007, Article 14 (DLD compilation); DLD FAQ. Read on 18 November 2026.
The ten-year duty is stated subject to the Civil Code's rules on contractor agreements, and Law No. 6 of 2019 concerns jointly owned property, which in our reading covers apartments and units in shared developments. The law says any agreement that contradicts these developer duties is void, and that owners keep any other rights they have under other legislation. Note what the law does not say: it speaks of installations and structure, not of "fit-out" or finishes as such, and we found no official rule that obliges a developer to allow an independent snagging inspection before handover. Ask for it in writing (our advice).
The 5% retention: why it matters for snagging
Dubai's escrow law (Law No. 8 of 2007, Article 14, per the DLD compilation we read) requires the escrow agent to keep 5% of the total value of each escrow account once the developer obtains the completion certificate, and to release it to the developer one year after the units are registered in the buyers' names. The DLD FAQ words the release point differently, as one year after completion or handover, and explains the purpose of this 5% retention: a guarantee that the developer or contractor deals promptly with defects that are clear at completion or appear within a year after handover.
In practice this gives buyers of off-plan property a window when the developer still has money held back (our reading). Report snags early and in writing, within that first year, so they are on record while the retention may still be in place (our reading). See escrow accounts in Dubai.
When to do a snagging inspection
- 1Before handover
Ask the developer for an inspection appointment once the completion certificate is issued; snag before you sign the handover papers.
- 2At handover
Record meter readings, keys and any remaining snags on the handover form.
- 3De-snagging
Re-inspect after the developer's repairs; close each item in writing.
- 4Before month 12
Because the installations warranty runs one year from handover, a second check before the anniversary is supported by the law.
The timing is our advice built on the legal periods. The Dubai Land Department's handover rules add that after the completion certificate the developer may not refuse to hand over or register the unit if you have met your contractual obligations.
Snagging checklist: what goes on a snag list
A typical snagging checklist for a Dubai apartment or villa covers (our list):
- Walls, ceilings: cracks, paint, damp
- Floors and tiles: level, hollow tiles, grout
- Doors and windows: alignment, seals, locks
- Electrical: sockets, switches, lights, panel
- Plumbing: leaks, pressure, drainage
- Air conditioning: cooling, noise, drainage
- Kitchen and bathrooms: fittings, sealant
- Balcony: drainage, railings
- Area: measured against the contract
For each item, record the room, a photo, a short description and a priority. A clear snag report with photos is easier for the developer to act on and easier for you to check later (our advice).
Checking the area at handover
The DLD FAQ sets a specific rule on size. If the unit's net area is smaller than the area in the sale contract, the developer must compensate the buyer for a decrease that exceeds 5% of the net area. If the unit is larger, the developer may not charge for the extra unless the contract expressly allows it. Area differences between the initial register, the contract and the title deed are checked against engineering drawings, if available. Measuring the unit during snagging is therefore worth the time.
Property snagging in Dubai: cost and companies
There is no official price list for snagging, and we found no regulator or licence specific to snagging firms; claims of a "RERA-approved snagging company" are not something we could confirm on any official page. Prices come from the companies themselves, so ask for a written quote that states what is inspected, whether thermal imaging and moisture testing are included, and whether a de-snagging visit is part of the price (our advice).
Compare firms in our snagging companies directory, or read our guide to choosing a snagging company in Dubai.
If the developer does not fix the snags
- Keep records. Dated snag list, photos, and the developer's replies.
- Escalate in writing. Refer to Article 40 of Law No. 6 of 2019 for installations and structure.
- Serious defects. Under Executive Council Resolution No. 6 of 2010, a buyer may apply to court to end the contract if, at handover, the unit is unfit for use because of material constructional defects.
- Building-wide issues. For common areas after handover, the owners committee and the management company are the route; see service charges.
We do not give legal advice; for a dispute, consult a lawyer.
After snagging: from Oqood to title deed
When the project is complete, the DLD says developers must register it, and fully paid units move from the initial register (Oqood) to the real estate registry, where the title deed is issued. The DLD's service for completing the initial procedures lists AED 250 for the title deed, AED 250 for the map, plus AED 10 and AED 10 where the registration fee was already paid. See Oqood and title deed in Dubai.
Snagging in Dubai: questions
What does snagging mean?
Inspecting a new property for defects (snags) and listing them for the developer to fix, usually before or at handover.
How long is the developer responsible for defects in Dubai?
One year from handover for installations such as electrical and plumbing, and ten years from the completion certificate for structural defects, under Law No. 6 of 2019.
What is a snag list?
A document listing each defect with its location, photo and description, given to the developer for repair.
What is de-snagging?
Re-inspecting after the developer's repairs to confirm each snag was fixed.
How much does snagging cost in Dubai?
There is no official price; companies set their own. Ask for a written quote with the scope.
Can I refuse handover because of snags?
The sources we read do not give a right to refuse handover. A buyer may ask a court to end the contract if the unit is unfit for use due to material constructional defects; for minor snags, list them in writing.
Sources
- Law No. 6 of 2019, Article 40 4 Sep 2019
- DLD: Dubai Real Estate Legislation (Law No. 8 of 2007; Resolution No. 6 of 2010) compilation, undated
- Dubai Land Department: Frequently Asked Questions read 18 Nov 2026
- DLD: completing the initial procedures (title deed) read 18 Nov 2026
See a figure that has changed? Write to info@emirae.pro and we will check it against the source. This guide is not legal advice.

Max runs Emirae.Pro, a directory of UAE businesses and property companies, and leads its property guides. Every source a guide cites is read before the guide goes live.